Introducing Manhours
Monday, 26 March 2007
Construction Computer Software

Candy (Estimating & Valuations) Topic:  Manhours

Man-hours: Once a production code has been implemented in Candy, a Man-hours report per Bill Item or Task code can be printed.
 
Candy summarises the productive resources (Plant and Labour) in the worksheet and prints the relevant report. i.e.

To complete Page 3 Item L, 20MPA Concrete to bases , the billed quantity is 1950m3. The number of skilled man-hours allowed to do the work is 5977 hours.

Therefore you have allowed 3.07 skilled man hours per m3 of concrete or conversely you must pour 0.33m3 per skilled man-hour. 
 
A similar report could be printed per Task code.

Task codes summarise bill items of a similar nature to provide both monetary and quantitive information.
For example all the Bulk Earthworks bill items are summarised to provide the total quantity of bulk earthworks and the total amount of money to complete the bulk earthworks.

A production report per Task code can be printed. i.e. Total Skilled Man-hours to complete x m3 of bulk earthworks.
 
 
To read more about Production Codes, refer to Sofware Documentation and download document 24 (Production Rates).

To read more about Task Codes, refer to Sofware Documentation and download document
18 (Job Analysis)